Belagavi: The Belagavi cantonment board has prepared an action plan of development works in its limits in the cost of Rs 5.32 crore. The board has already conducted the tender process and through which it has selected five contractors.

Belagavi cantonment board has planned to take up the road, gutter concrete work, development of the garden, park in the open land, proper supply of drinking water, repair of the Drainage line and repair of school classrooms in the camp limits of Belagavi city. The chief executive officer of the board Barschaswa has informed of taking these works in the board meeting held on Tuesday.

The board has prepared the action plan of taking up a total of seven works in the cost of Rs 5, 32, 4392. The officials have asked the contractor to provide the work details and the total cost of the expenditure of the work.

Work details
1)park development Madras A street-Rs1.43 lakh
2)Gutter concrete work at Moshi lane-Rs 1,33,547
3)School repair at Old post office road -Rs 59,35,497
4)Park development at Beef butcher street road Rs 3,32, 497
5)Paver installation at Old post office road -Rs 4,14,747
6)water pipelines repair at Parade road -Rs 18, 66,963
7)Set up of RO drinking water unit-Rs 4.39 Lakh.